The Study consists of eight tasks:

Task Start Completion
Task 1 - Project Management Spring 2012 Summer 2013
Task 2 - Public Outreach   Spring 2012 Summer 2013
Task 3 - Data Collection/ Needs Assessment Spring 2012 Spring 2012
Task 4 - Formulate Project Goals & Objectives and Evaluation Criteria Spring 2012 Summer 2012
Task 5 - Identification of Alternatives & Project Initiation Package Spring 2012 Summer 2012
Task 6 - Traffic Impact Assessment Spring 2012 Winter 2012/2013
Task 7 - Offline Ridership Model Spring 2012 Spring 2013
Task 8 - Alternatives Analysis Summer 2012 Summer 2013
 
 
© 2013 LYNX
Central Florida Regional Transportation Authority
Website maintained by VHB
Get Involved  |  About the Study  |  News  |  Study Documents  |  Presentations
Partners  |  Contact Us  |  Site Map  |  Facebook  |  Twitter